Electronic Construction Collaboration System - Phase III

Researcher(s)

Principal investigators:

Student researcher:

Project status

Completed

Start date: 07/01/10
End date: 06/30/11

Publications

Report: Electronic Construction Collaboration System - Phase III (4.40 mb pdf) December 2011

Sponsor(s)/partner(s)

Sponsor(s): Iowa Department of Transportation

About the research

Abstract:

This phase of the electronic collaboration project involved two major efforts: 1) implementation of AEC Sync (formerly known as Attolist), a web-based project management system (WPMS), on the Broadway Viaduct Bridge Project and the Iowa Falls Arch Bridge Project and 2) development of a web-based project management system for bridge and highway construction projects with less than $10 million in contract value.

During the previous phase of this project (fiscal year 2010), the research team helped with the implementation process for AEC Sync and collected feedback from the Broadway Viaduct project team members before the start of the project. During the 2011 fiscal year, the research team collected the post-project surveys from the Broadway Viaduct project members and compared them to the pre-project survey results.

The results of the AEC Sync implementation on the Broadway project were positive. The project members were satisfied with the performance of the AEC Sync software and how it facilitated document management and its transparency. In addition, the research team distributed, collected, and analyzed the pre-project surveys for the Iowa Falls Arch Bridge Project. The implementation of AEC Sync for the Iowa Falls Arch Bridge Project appears to also be positive, based on the pre-project surveys.

The fourth phase of this electronic collaboration project involves the identification and implementation of a WPMS solution for smaller bridge and highway projects. The workflow for the shop drawing approval process for sign truss projects was documented and used to identify possible WPMS solutions. After testing and evaluating several WPMS solutions, Microsoft SharePoint Foundation’s site pages were selected to be pilot-tested on sign truss projects. Due to the limitation on the SharePoint license that the Iowa Department of Transportation (DOT) has, a file transfer protocol (FTP) site will be developed alongside this site to allow contractors to upload shop drawings to the Iowa DOT. The SharePoint site pages are expected to be ready for implementation during the  2012 calendar year.