I-394 Business Impacts Case Study

Project Details
STATUS

Completed

START DATE

01/01/03

END DATE

12/31/03

RESEARCH CENTERS InTrans, CTRE
SPONSORS

Howard R. Green

PARTNERS

Minnesota DOT

Researchers
Principal Investigator
David Plazak

About the research

The Minnesota DOT is contracting with a team of consultants led by Howard R. Green to conduct a detailed analysis of the long-term impacts of access management treatments on a section of Interstate 394 in the Twin Cities metropolitan area that was upgraded from an urban expressway to a full access control Interstate roadway.