Implementation Evaluation of the Rustic Road Geosynthetic Reinforced Soil-Integrated Bridge System

Project Details
STATUS

Completed

START DATE

09/01/15

END DATE

10/30/17

RESEARCH CENTERS InTrans, CEER, CTRE, MTC
SPONSORS

Midwest Transportation Center
Missouri Department of Transportation
USDOT/OST-R

Researchers
Principal Investigator
Andrew Boeckmann

University of Missouri - Columbia

About the research

Deficient small bridges are a significant concern for the nation’s transportation infrastructure, so advancing the implementation of time- and money-saving technology is essential to maintaining a “state of good repair.”

Geosynthetic-reinforced soil-integrated bridge systems (GRS-IBS) technology has the potential to introduce significant time and cost savings on small bridge replacements by removing the need for driven piles. Unfamiliarity with the technical performance and construction operations has impeded implementation.

The goal of this project is to advance the implementation of the technology by evaluating the construction and early service life performance of the Rustic Road GRS-IBS, which was constructed in early 2015, in Boone County, Missouri. This detailed case study was coordinated with the results of a concurrent Midwest Transportation Center effort also focused on advancing implementation of these types of bridge systems.


Funding Sources:
Midwest Transportation Center
Missouri Department of Transportation ($34,999.00)
USDOT/OST-R ($34,999.00)
Total: $69,998.00

Contract Number: DTRT13-G-UTC37